Link to Adkins' Services.jpg (3299 bytes) Recent Engagements.jpg (7501 bytes)

EXPERT TESTIMONY/CONTRACT DISPUTES

SUCCESSFUL VERDICTS

  • Expert testimony before the Armed Forces Board of Contract Appeals on behalf of a contractor who was terminated for untimely performance on two multi-million dollar Navy procurement contracts. Schedule analysis testimony quantified the contract delays and attributed their cause to owner design errors. Successful verdict converted a termination for default to a termination for convenience and awarded the contractor $25 million of damages.
  • Engagement by the Department of Justice to provide expert testimony on scheduling, construction and damages issues to defend the U.S. Coast Guard against a $6.5 million contractor claim alleging changed site conditions, design errors, and owner interference on a major housing project in Kodiak, Alaska. Quantifying numerous errors of the prime contractor and its subcontractors, Adkins' testimony refuted the applicability of a total cost approach. Adkins' discrete delay and damage analyses demonstrated that the overruns were not caused by the government and therefore the contractor's entitlement and quantum were severely limited.
  • Cost estimating and financial testimony on behalf of a New York City electrical contractor before a three-member arbitration panel; successful defense in that the plaintiff was awarded only 15% of the $5 million claimed.
  • Delay and damage analyses for a professional liability carrier defending a design firm from a $7.5 million contractor claim involving two major tunnel contracts in Rochester, New York. Engagement encompassed claims analyses, technical input and litigation support that culminated with the incorporation of Adkins' findings in a summary judgment motion, which was successful in dismissing the suit against the designer.
  • Technical advice and litigation support assisting Armco, Inc. in the defense of an $8 million warranty claim alleging faulty construction on a $25 million water tunnel project. After Griffith’s testimony, one week into the trial, the judge issued a directed verdict dismissing the claim in its entirety.
  • Expert arbitration testimony assisting a wrongly defaulted, specialty foundation subcontractor in receiving a favorable, $1 million judgment against a major environmental general contractor on a $54 million EPA Superfund Cleanup in New Jersey. Our affidavit and exhibits demonstrated the "cardinal change" impact nature of a changed site condition.

HEADBAR3.JPG (21747 bytes)

 

SUCCESSFUL DEPOSITIONS/NEGOTIATED SETTLEMENTS

 

  • Claim preparation, advice and assistance to quantify delay impact costs on behalf of a mechanical construction contractor in Reno, Nevada which resulted in a favorable $580,000 recovery.
  • Prepared a schedule analysis and critique of damages in an extremely short time frame for a large Virginia highway contractor. Adkins’ findings resulted in the subcontractors reducing their claims substantially, resulting in a favorable settlement for our client.
  • Technical and claim analyses on behalf of a heavy/highway construction contractor and its bonding company to substantiate a claim that an $18 million New York State highway and bridge rehabilitation project contained numerous, unresolved design errors and therefore the contractor was improperly terminated. The bonding company was justified in refusing to complete the defaulted contract and a $5 million favorable settlement was negotiated to the benefit of the contractor and surety just before the trial was to commence.

 

HEADBAR3.JPG (21747 bytes)

 

PENDING LITIGATION

HEADBAR3.JPG (21747 bytes)left.h5.jpg (873 bytes)

BACK TO REPRESENTATIVE ENGAGEMENTS

[To Services]  [To Who Are Adkins Clients]   [To Adkins Professionals]